6400052312 Repair & Reconditioning of Pipelines, Abqaiq Area. Saudi Aramco Abqaiq Contracts Admi. Unit July 2002 - 30 Jun 06
6600004161 Construct Oily Water Treatment System @ Yanbu Crude Oil Terminal Saudi Aramco Yanbu Crude Oil Terminal Aug–2002 Jul–2003
47027/00 Construction of Internal Security Forces Quarters at Hawtah Saudi Aramco Hawtah Field Units Sep–1997 Jul–1998
PURCHASE ORDERS-VARIOUS Mitsubishi Heavy Industries Ltd. at Ghazlan II Power Plant Proj. (SEC) Mitsubishi Heavy Ind.,Ltd. for SEC Ghazlan 1999-2005
41210/00 Repair of Electrodialysis Building at Uthmaniyah Gas Plant Saudi Aramco Uthmaniyah Gas Plant Apr–1999 Jan–2000
SE/83829/WO/32 Reinforcement of East/Central Tie Lines:> Crude Oil Stabilization National Cont. Co. for SEC Khurais 2004
42451/00 Construct Security Guardhouse at West Pier, Ras Tanura Saudi Aramco West Pier, Ras Tanura Nov–1999 Dec–2000
6140061439 Waste Oil Recovery System Construction Saudi Aramco UGOSP – 9 Jun–2002 Aug–2002
6510093275 Work at the Grand Canyon (Earthworks & Const. of Oily Water Treatment Ponds) Saudi Aramco Abqaiq Plants, Abqaiq Aug–2004 Nov–2004
400572–011 Replace Shedgum & Udhailiyah A/C System Saudi Aramco Shedgum & Udhailiyah Feb–1999 Aug–1999
6140064289 Upgrade Oily Water Sewer at Sludge Catcher Area IOK Saudi Aramco IOK Utilities Plant, UGP Mar–2002 Aug–2002
400513–058 Shaybah AXL DCS/Isolation Saudi Aramco Abqaiq Plants May–1998
400529–011 Cathodic Protection Upgrade Saudi Aramco Uthmaniyah Gas Plant Jul–1997 Sep–1997
400513–049 Foundation Constructions Saudi Aramco Abqaiq Plants Nov–1997 Feb–1998
400635–064/ 6140063564 Substation #17 & #27 Loads Diversification, Plant 100 Saudi Aramco Abqaiq Plants Apr–2002 Dec–2002
400501–054 Upgrade Road and Reinforce Well Pad Saudi Aramco Hawtah Field Apr–1998 Oct–1998
400501–065 Upgrade Road & Reinforce Well pad Saudi Aramco Hawtah Field Oct–1998 Jan–1999
400359–099(R1) Concrete Cable Trench Repair Saudi Aramco QSWTP Dec–1995 Sep–1996
400604–019 LAN Connection & Asphalt Paving Saudi Aramco Shedgum Gas Plant Apr–2001 Oct–2001
6510029358 Replacing SSP to RTR Piping, HGP Saudi Aramco Hawiyah Gas Plant Sep–2003 Nov–2003
400539–014(R1) External Fire Proofing of Substations Saudi Aramco Abqaiq Plants Oct–1997 Feb–1998
400502–076 Construct Fireproofing of Substation Saudi Aramco Electrical Plant, Abqaiq Apr–1997 Sep–1997
400345–014 Security Access Control System Installation Saudi Aramco Abqaiq GOSP–3, 4, 5 & Shdgm.–4 Sep–1998 Nov–1998
400534–046 Concrete Foundation Repair Saudi Aramco Sulfur Area, Shdgm. Gas Plant Dec–1997 Feb–1998
400534–002 External Fire Protection Saudi Aramco SHGP Substation R42–P6, R42–P7 Apr–1997 Nov–1997
400630–034/ 6140063034(R1) Clean The North Sediment Basin at QSWTP Saudi Aramco QSWTP Mar–2002 Jun–2002
400337–045 Renovate Offices MSO Warehouse Saudi Aramco QSWTP Nov–1993 Jan–1994
400507–056 10” Gravity Sewer Line Replacement Saudi Aramco Ain Dar GOSP #1 Nov–1996 Mar–1997
6510080226 Modify Existing GOV Instr. & 1" Regulators Piping at 12" HDWGT–1 Fuel Gas Line Saudi Aramco Haradh Gas Plant May–2004 Oct–2004
400502–036 Install Min. Flow Recycle System Saudi Aramco North Steam Plant, Abqaiq Dec–1996 Apr–1997
6140061425 (R2) Waste Oil Recovery System Construction Saudi Aramco UGOSP – 9 Oct–2001 Apr–2002
400512–023(R1) Modification Flare Drip Leg Saudi Aramco Plant–120, Abqaiq Plants Mar–1997 Apr–1998
6510010849 Construction of NGPD R/V Shops Building Extension Saudi Aramco Abqaiq Plants Oct–2002 Dec–2002
400359–047 + Change Order Intake & Transfer Area Concrete Repair Saudi Aramco QSWTP Mar–1993 Jun–1993
400502–004 (RA) Boiler – 9 Stack Foundation Repair Saudi Aramco North Steam Plant, Abqaiq Feb–1996 Apr–1996
400337–035 Dry Storage Warehouse Modifications Saudi Aramco QSWTP Aug–1993 Sep–1993
400621–027 Construct Two Engineering Offices Saudi Aramco Abqaiq GOSP Services Apr–2001 Dec–2001
6510060962 Supply & Install Fire Monitors & Hydrants Saudi Aramco Haradh Gas Plant Jan–2004 May–2004
400311–097 Modification of Gas Tank 1 & 2, 7 LPG Tank Saudi Aramco Fire Trng. Cntr., Plant 206,Abqaiq Jun–1997 Sep–1997
CT/T–4149–1–04 Re–Wrapping of Gas Pipelines from Shedgum to Hofuf Plant Saudi Cement Co. Dammam/Hofuf/ Shedgum Jan–2004
400534–005 Power Cable Layout on Cable Tray Saudi Aramco Shdgm. GP Utilities Area May–1997 Jun–1997
400507–039(R1) Relocation of Sour Water Pit Saudi Aramco Ain Dar GOSP #4 Feb–1997 Jun–1997
6140064292 ESD Modifications / Sulphur Train–1 / UGP Saudi Aramco Uthmaniyah Gas Plant Feb–2002 Apr–2002
400642–036 Upgrade Utilities Chemical Facilities Saudi Aramco Uthmaniyah Gas Plant Mar–2002 Jun–2002
400384–009 Radio Workshop Saudi Aramco Udhailiyah Apr–1993 Jun–1993
6140064292(R1) ESD Modification / Sulphur Train–1/ UGP Saudi Aramco Uthmaniyah Gas Plant Feb–2002 May–2002
045335–052(R1) Refurbish Building 101 at Udhailiyah Industrial Park Saudi Aramco Udhailiyah Industrial Park Nov–1998 Feb–1999
400539–046(R1) Deaerators Foundation Repair Saudi Aramco Abqaiq Plants Sep–1998 Mar–1999
400384–037 Hammam at Qatif Junction Saudi Aramco Qatif Junction Comm. Site Jul–1995 Jan–1996
400225–086 Installation of Cable Tray Saudi Aramco Plant #462, Abqaiq Plants Nov–1992
400469–082(R1) Fabrication and Installation of Flow–Meter Saudi Aramco Abqaiq Well #145 Nov–1005 Feb–1996
400604–021 BI – 3141 SAPMT Site Office Services Saudi Aramco Shedgum Gas Plant Oct–2001 Dec–2001
400502–025 Repair /Replace Concrete Foundation Saudi Aramco South Steam Plant, Abqaiq Aug–1996 Oct–1996
400634–016 Inspection Worksheet, Abqaiq Plants Saudi Aramco Abqaiq Plants Sep–2000 Jan–2001
400440–079 Installation of Unloading Pump Saudi Aramco RMU Plant, Uth. Gas Plant Dec–1994 Jan–1995
400616–003 Construction of Coating / Blasting Shops and Hydrotest Shelter Saudi Aramco CGMSD Fabrication Shop Feb–2001 May–2001
400356–049 Concrete Foundation Repair Saudi Aramco UWIP – 5 Nov–1994 Jan–1995
400379–044(R1) Upgrade PZV Workshop Saudi Aramco Shedgum Gas Plant Jan–1993 Apr–1993
400290–063(R3) Construct Offices Saudi Aramco Ain Dar Field Services Building Jul–1993 Mar–1994
400440–062(R2) Repair and Renovate Burn Pit Saudi Aramco Uthmaniyah Gas Plant Jul–1994 Feb–1995
400384–049 Tanajib Plant & Marine A/C Saudi Aramco Tanajib Plant & Mar. Coms. Sites Apr–1996 Oct–1996
400553–025 Repair / Replace Faulty Anodes Saudi Aramco Shedgum Gas Plant Apr–1998 Jul–1998
400621–029 Demolish and Remove Abandoned Stations Saudi Aramco Abqaiq Apr–2001 May–2001
400472–096 Fabricate & Install Pump Screens Saudi Aramco North Stabilizer, Abqaiq Plants Jun–1996 Aug–1996
400384–025 Pump St. #2 Stand–By A/C Upgrade Saudi Aramco Pump St.–#2 Oct–1994 Mar–1995
400356–081 Install Gaitronics Syst. at UWIPS–3 Saudi Aramco Uthmaniyah WIPS–3 Jul–1997 Sep–1997
400518–034(R1) Replacement of Two– (2) 1½” Ball Valves Saudi Aramco Ain Dar–1&3 SWD System Jan–1997 May–1997
400502–095 Reducing Station #2 Upgrade Saudi Aramco North Steam Plant, Abqaiq Dec–1997 Feb–1998
400502–023(R2) Installation of Cathodic Protection Saudi Aramco Air & Water Plant, Abqaiq Jul–1996 Jan–1997
400495–007 Process Area Flooring & Foundations Saudi Aramco QSWTP Aug–1996 Nov–1996
6510010757 Construction of the Radiation Storage Pit Saudi Aramco Hawiyah Gas Plant Nov–2002 Mar–2003
400356–057 Gaitronics Communication System Construction Saudi Aramco UWIP – 4 Jul–1995 Sep–1995
400479–027(R1) Septic Tank & Leach Field Construction Saudi Aramco UGOSP – 8 Sep–1995 Jan–1996
400470–045 Supply Experienced Pipe Fitters Saudi Aramco Shedgum Gas Plant Mar–1995 Apr–1995
400490–075 Modification in Saudi Aramco P/L Cleaning Facilities, Utility Area Saudi Aramco Uthmaniyah Area Mar–1996 Apr–1996
400394–071(R1) Choke Valves Installation Saudi Aramco Abqaiq, Ain Dar & Shedgum Areas Nov–1993 Mar–1994
400424–040 Relocation of Two– (2) Portables to Abqaiq Saudi Aramco Harmaliyah & Abqaiq Aug–1994 Feb–1995
400490–072(R1) 10” UTMN–1225 Jump Over to Uthmaniyah GOSP–4 SWD System Saudi Aramco UTMN – 1225 Mar–1996 Jul–1996
400487–030 Relocate AOV's Instrument Airlines Saudi Aramco NGL, Abq Plants Jul–1996 Jul–1996
400518–051 Affix Acctg. Plant Tags & Removal of Sect. of Abandoned Abq.– 3 F/L Saudi Aramco Abqaiq–3 F/L May–1997 Sep–1997
400356–074 Install Gaitronics System at UWIP–1 Saudi Aramco UWIP #1 Feb–1997 Apr–1997
400488–034 Demolition of Diesel Tank Saudi Aramco Abq. Bulk Plant, Plant – 279 May–1997 Aug–1997
400440–042(R1) Maintain Administration Building Saudi Aramco Uthmaniyah Gas Plant Jun–1994 Oct–1994
400337–044 24” Manholes for Tanks PLT 423 Saudi Aramco UWSS – 1 Oct–1993 Dec–1993
400621–046/ 6140062146 Modification of Existing R/V Platforms, HPPT D–100B Saudi Aramco Abqaiq GOSP #3 Jun–2002 Aug–2002
400459–031(R1) Replace Deaerator E – 28 Funnel Saudi Aramco North Steam Plant, Abqaiq Jul–1994 Oct–1994
400384–008 Civil Expansion of Building – 316B Saudi Aramco Dhahran Feb–1993 Mar–1993
85054–70 Renovation of Western & Eastern Toilets at Faraz & Uth. Power Plants SCECO Faraz & Uth. Gas Plants 1415–05–10 1415–07–10
400529–073 Relocate Cathodic Protection Anodes Saudi Aramco Uthmaniyah Gas Plant Dec–1997 Jan–1998
400550–080(R1) Replace Overhead Power Line with Underground Saudi Aramco Abqaiq May–2003 Jul–2003
400439–039 Fabrication Shop Construction Saudi Aramco Hawiyah GOSP-2 Support Unit Aug–1995 Oct–1995
400046–057 Fazran and Ain Dar GOSP #6 Termicide Saudi Aramco Fazran & ADG–6 Com. Sites Jan–1995 Apr–1995
400507–058 HPPT R/V Platform Extension Saudi Aramco Ain Dar GOSP – 2 Dec–1996
400465–078(R1) Fire – Water System Piping Replacement Saudi Aramco Ain Dar GOSP #1 Oct–1995 Feb–1996
400673–026(R1)/ 6140067326 Grounding Modifications, Substation #15, Plant – 120 Saudi Aramco South Stabilizer, Abqaiq Plants Jul–2002 Oct–2002
400418–032 Replace 8” Diameter RW Piping Saudi Aramco Dhahran Main Camp Dec–1993 Jan–1994
400651–061/ 6140065161 Rectify Items for Executive Review, SHDGM Saudi Aramco Plant Wide Shdgm. Gas Plant Mar–2002 Apr–2002
400420–089 Construct Concrete Pad Saudi Aramco Abqaiq Main Camp May–1995 Aug–1995
400359–074 HPS Area Concrete Repairs Saudi Aramco QSWTP Aug–1994 Oct–1994
400472–034 Fabricate and Install Platforms Saudi Aramco APS 4 & 5, Abqaiq Plants Dec–1994
400483–048 Renovation of Interior of Building 12–412 at Abqaiq Camp Saudi Aramco Abqaiq Camp Building #12–412 Jul–1995 Sep–1995
400488–061 Office Renovation at Building 3017 Saudi Aramco Bldg.3017, Old Abq. Rd., Dh. Nov–1998 Dec–1998
6140400632 Replacement of 24” Carbon Steel Pipe with 20” RTR Pipe Saudi Aramco UWIPS #4 May–2001 Jun–2001
400635–044 Construct New Guardrails Saudi Aramco Abqaiq Plants Mar–2001 Jun–2001
400431–004 Laboratory Interior Renovation Saudi Aramco Abqaiq Laboratory Feb–1994 Mar–1994
400311–094 Provide Pipe Fitter for Ain Dar Area Saudi Aramco Ain Dar Area Apr–1997 Dec–1997
400267–085(R1) Install Parking Sunshade Saudi Aramco Udhailiyah Admin. Building Jan–1999 Apr–1999
400267–073(R1) AAA Garage Electrical Upgrade Saudi Aramco Udhailiyah Camp Feb–1998 Mar–1998
400311–093 Provide Pipe Fitters for Abqaiq Area Saudi Aramco Abqaiq Area Mar–1997 Jun–1997
400472–078 PCV 7A / B Power Supply Saudi Aramco UA Spheroid, Abqaiq Plants Dec–1995 Feb–1996
400524–034 Flare Line Expansion Loop Found Saudi Aramco UGOSP #9 May–1997 Jun–1997
400337–040 Remove Steel Fittings from IPS Saudi Aramco IPS Facility Sep–1993 Nov–1993
400483–015 Renovate Exterior Walls of Carpenter ad Paint Shop at Abqaiq Saudi Aramco CMD Abqaiq Dec–1994
400397–068 Replace Motor Starter Saudi Aramco N/Steam Plant, Abqaiq Jan–1993 Apr–1993
400634–075 Installation of Motor Actuator HV–6669, UA Spheroids, Abqaiq Plants Saudi Aramco Abqaiq Plants Oct–2001 Feb–2002
400376–090 Fabricate and Install Barricades Saudi Aramco PLT–332/337, NGL, Abq. Plant Oct–1994 Nov–1994
400490–048(R2) Ain Dar GOSP #1 Header Extension Saudi Aramco Ain Dar GOSP #1 Dec–1995 Mar–1996
400472–013 Construction of Concrete Supports Saudi Aramco Plant 142, APS#7, Abqaiq Oct–1994 Nov–1994
400425–086(R1) Construct Lube Oil / Paint Shed Saudi Aramco PLT 110, N/Stabilizer, Abq. Jun–1994 Sep–1994
400472–035 Fabricate & Install Platforms Saudi Aramco UA Spheroid, Abqaiq Plants Dec–1994 Dec–1994
42360/00 Upgrade, Oily Sewer Water System Construciton, West Pier. Saudi Aramco Ras Tanura July 2000 - Dec 2001
400552–046 Substation 15/20 Metal Doors Saudi Aramco Abqaiq Plants Apr–1999 May–1999
400635–041 Installation of Instrument Air Dryer, Plant – 100 Saudi Aramco Abqaiq Plants Oct–2001 Nov–2001
400360–059 Certified Crane Operators Saudi Aramco Abqaiq GOSP #2 Oct–1993 Nov–1993
400490–076 Modification in SA P/L Cleaning Facilities Saudi Aramco Aqaiq Area Mar–1996 Apr–1996
400397–061 Install Transformers & Resistors Saudi Aramco Plant–111, Abqaiq Plants Feb–1993 Mar–1993
400444–088(R1) Fabricate Pipeline for Fire Monitor Saudi Aramco Shedgum GOSP #4 Jul–1995 Aug–1995
400518–025 Installation of Guardrails Saudi Aramco Shedgum Field Nov–1996
400623–026/ 6140062326(R1) Repair Concrete Foundations, Ain Dar GOSP #3 Saudi Aramco ADGOSP – 3 Oct–2001 Apr–2002
400632–043 Launcher & Receiver Piping Modification Saudi Aramco UWIPS #4 & #5 Aug–2001
400507–095 Repair Underground Water Leak Saudi Aramco K–201ASKID, Ain Dar GOSP #4 Jan–1997 Mar–1997
400266–008 Redesign Safety Bulletin Boards Saudi Aramco North & South Gates, Abqaiq Plant Dec–1996
400850–051 Mothball 98 Housing Units Saudi Aramco Abqaiq Camp Mar–1994 May–1994
400552–021 Modification Flare Drip Leg Saudi Aramco Plant–120, Abqaiq Plants Apr–1998 Jul–1998
400420–074(R1) Replace Transformer T – 601 Saudi Aramco Ain Dar Station #1 Nov–1994 Apr–1995
400361–099 Vessel Cleaning T & I Saudi Aramco Shedgum GOSP #5 Nov–1993 Dec–1993
400440–047(R1) Install Foundations K108B Comp. Saudi Aramco Uthmaniyah Gas Plant May–1994 Aug–1994
400535–045 Platform Installation of GT – 1 Saudi Aramco Ain Dar WIP #1 Nov–1998 Dec–1998
400459–099 Repair Concrete Foundations Saudi Aramco North Steam Plant, Abqaiq Plants Jan–1996 Mar–1996
400376–072 Upgrade Air Conditioning Systems Saudi Aramco Abqaiq Plants Jun–1994 Jul–1994
6140062014(R1) Install Two Jib Cranes for R/V Shop Saudi Aramco UDH. UTC BLDG. Aug–2001 Oct–2001
400472–083 Fabricate and Install Cable Tray Saudi Aramco North Stab., Abqaiq Plants Dec–1995 Jan–1996
400376–054(R1) Fabrication & Installation of PCV–505 Supports Saudi Aramco Abqaiq Plants May–1993 Aug–1993
400623–026/ 6140062326(R2) Repair Concrete Foundations, Ain Dar GOSP #3 Saudi Aramco Ain Dar GOSP–3 Oct–2001 Apr–2002
400444–099 Substation Foundation Repair Saudi Aramco Shedgum WIP #2 Sep–1995 Dec–1995
400561–020 Fabricate Sixty– (60) Ladders for Rectifiers Saudi Aramco Contractor's Yard Aug–1998 Sep–1998
400420–002 Install Anchors Saudi Aramco Sub–50, Abqaiq Plants Jan–1993
6510009844 ESD Modification Saudi Aramco Uthmaniyah Gas Plant Sep–2002 Sep–2002
400502–006 Removal of Abandoned Equipment Saudi Aramco Air & Water Plant, Abqaiq Feb–1996 Mar–1996
400465–016 Fabricate and Install Platforms Saudi Aramco Ain Dar GOSP #1 Aug–1994 Sep–1994
400651–015 Excavation to Repair Water Leaks, 10” RTR, Utilities Area Saudi Aramco Shedgum Jun–2001 Jul–2001
400651–015 Excavation to Repair Water Leaks, 10” RTR, Utilities Area Saudi Aramco Shedgum Jun–2001 Jul–2001
400469–019 Fabricate and Install Platforms Saudi Aramco Abqaiq GOSP #6 Oct–1994
400472–002 Ground the Smoking Stand Saudi Aramco N/Stabilizer, Abqaiq Plants Sep–1994 Oct–1994
400362–090 Fabricate and Install Platforms Saudi Aramco Ain Dar GOSP #4 Jan–1994 Feb–1994
400470–017(R1) Repair Portable Clinic Building Saudi Aramco Harmaliyah Camp Sep–1994
400469–087 Fabricate and Install Walkways Saudi Aramco Abqaiq GOSP #5 Dec–1995 Jan–1996
400290–081 Installation of Wooden Sign Boards Saudi Aramco Ain Dar Area Nov–1994 Dec–1994
400267–028 Udhailiyah Airport Clean – up Saudi Aramco Udh. Village & Udh. Airport Area Mar–1993
400483–037 Renovation of Laboratory Room at Abqaiq Building 9–311 Saudi Aramco Bldg. 9–311, Abqaiq Camp May–1995 Jul–1995
400379–061 Upgrade Transformer CPRUTL Saudi Aramco Shedgum Gas Plant Sep–1993 Oct–1993
400423–036 Fabricate and Install Job Cranes Saudi Aramco APS–7, Abqaiq Plants Jul–1994 Sep–1994
400507–077 Making / Blocking New Existing Entrance Saudi Aramco ADGOSP #2 Mar–1997 Apr–1997
400360–026 Fabricate and Install Steel Platforms Saudi Aramco Abqaiq GOSP #5 Oct–1992 Nov–1992
400290–071 Install Conduits Radios and Telephones Saudi Aramco Field Srvcs. Bldg., Shedgum Jul–1994
400553–053 Excavation to Replace Cable Saudi Aramco Shedgum Gas Plant Jul–1998 Aug–1998
400465–067 Construct A Platform Saudi Aramco Ain Dar GOSP #3 Aug–1995 Oct–1995
400360–027 Fabricate and Install Walkways Saudi Aramco Abqaiq GOSP–#2&#6 Oct–1992 Nov–1992
400472–011 Fabricate and Install Guardrails Saudi Aramco Abqaiq Plants Oct–1994 Nov–1994
400469–004(R1) Cable Excavation and Concrete Footings Saudi Aramco Abqaiq GOSP #6 Jun–1994 Jul–1994
400337–036 MSO Warehouse Roof Repairs at QSWTP Saudi Aramco QSWTP Sep–1993
400465–002 Fabricate ad Install Platforms Saudi Aramco Ain Dar GOSP #1 Apr–1994 May–1994
400469–006 Fabrication and Installation of 2” Ø Flushing Line Saudi Aramco Abqaiq GOSP #2 Jul–1994
400510–061 Fabrication Wooden Plugs Saudi Aramco Shedgum Gas Plant Dec–1996
400440–065 Construct Foundation Sun Shield Saudi Aramco Uthmaniyah Gas Plant Aug–1994 Sep–1994
400472–036 Fabricate and Install Supports Saudi Aramco North Stabilizer, Abqaiq Plants Dec–1994
400425–081 Construct Pipe Support Saudi Aramco PLT 110, N/Stabilizer, Abq. Jul–1994 Aug–1994
400459–072(R2) Fabricate Wooden Plugs Saudi Aramco South Steam Plant, Abqaiq Jun–1995 Jul–1995
400362–029 Fabricate and Install Supports Saudi Aramco Ain Dar GOSP #1 Oct–1992 Nov–1992
400566–067 Repair U/Ground Leak at NCR (Tube Repair Only), North Control Room Saudi Aramco Abqaiq Plants Aug–2001
400425–044 Clean Trenches Under Fin – Fans Saudi Aramco Abqaiq Plants Oct–1993 Oct–1993
400440–068 Re – Slope ED Building Floor Saudi Aramco Uthmaniyah Gas Plant Aug–1994 Sep–1994
400540–053 Guardrail Posts Installation Saudi Aramco Ain Dar GOSP #4 Sep–1998 Nov–1998
400502–090 Installation of Cathodic Protection Saudi Aramco Air & Water Plant, Abqaiq Jan–1997 May–1997
400425–098 Excavate Buried Supports Saudi Aramco APS#7, Abqaiq Plants Aug–1994 Sep–1994
400362–027 Repair Fazran Security Building Saudi Aramco Fazran Security Building Oct–1992
P-002-C-032-B-1 CONTRACT FOR SITE PREPARETION, FILLING AND ROAD CONSTRUCTION WORK KCC/SIPCHEM JUBAIL JUNE-2005
JUNE-2006
82300-COB-FC PURCHASE ORDERS - VARIOUS SAUDI ARABIAN BECHTEL GHAZLAN JULY 2002- JUNE 2004
SEC-EOA-30431061-00 230KV OVERHEAD TRANSMISSION LINE FROM JEDIDAH TO NEW JAWATHA NCC/SCECO HOFUF JUNE-2005
DEC-2006
6510130900 LIGHTING AND HVAC UPGRADE PROJECT Saudi Aramco SHEDGUM APRIL-2005
SEP-2005
6510073376 Install Additional Tast Lighting in Oil Processing Area Saudi Aramco Abqaiq Plants May–2004 Apr–2005